TerraSlave: No active task

Problem:

When attempting to run a macro on a project using TerraSlave and the following message is reported in TerraSlave’s Monitor Active Task dialog, try the following steps:

No active task

Probable Resolution#1:

In your Terra installation folder, open your TSlave folder. Then clear the contents from the following folders: ‘progress’, ‘queue’, and ‘task’.

TSlave Folders

Probable Resolution#2:

Ensure that the TerraScan project is saved prior to attempting to run the macro. Open the tsk file found in the “task” folder and the “Project” line should not be blank. If it is blank, the project wasn’t saved. If it contains a project, then verify there are project blocks in the prj text file using a text editor as perhaps you saved it prior to defining project blocks.

Share

GeoCue Group Support

GeoCue Group Support has written 630 articles

Leave a Reply